The Bremen-situated planner and operator wpd takes positive stock for the construction of the offshore windfarm Butendiek. “We are about to complete pile driving, we are well within our time schedule and we have fallen short of the predefined sound levels”, Achim Berge Olsen, managing director of Butendiek and wpd offshore, is pleased to announce. Of the 80 foundation structures for the wind turbines, 71 have been erected since April – presumably, construction will be completed by the beginning of next week. Subsequently, the transition pieces, the connecting pieces between the foundations and the turbine towers, will be set, a third of which have already been installed. The substation has been erected at the end of May as scheduled.

“We have shown that we have been successful with our modern sound protection measurements. We have fallen short of the predefined sound levels and overall, we have reached the best levels of all wind farms that have been erected in the North Sea so far”, Berge Olsen says. The analysis of the data from the accompanying ecological monitoring shows no measurable differences in the population of the common porpoise in the surroundings of the offshore wind farm Butendiek. Elaborate counting by plane and ship examining the protected ecological assets birds and maritime mammals as part of the accompanying ecological monitoring will be conducted by independent experts from the Husum-based Bioconsult GmbH for at least two years before construction start, during the complete construction phase and for 3 – 5 years during the operational phase, as provided by BSH Standard Meeresumwelt (BSH Standard Maritime Environment). “Analysis of the data shows that the common porpoise is still present in the surroundings of the construction site, furthermore there was no evidence as to a decrease in the population. For us, this means that our elaborate and cost-intensive sound protection measurements are effective and working”, Berge Olsen says.

Both POD stations in long-term operation where the presence of common porpoises has been recorded acoustically have shown levels this year that conform to the experiences of the years before. “The number of common porpoises at both POD stations has increased since March of this year due to seasonal reasons. There is no trend towards a decrease in numbers. At the BU1 station, which is close to the construction site, the highest level has been recorded in May and June. Population development and population level are thus normal and the quantity of common porpoises is the same as in previous years”, Berge Olsen reports.

Appropriate short reports with hydrosound and C-POD results have been drafted within a few days after the construction of the foundations, at the beginning for each single site, in the meantime for every four sites and the corresponding pile drivings, and submitted to the competent authorities, BSH, BMU, BfN, UBA, BMWI and BMVBS. “We appreciate the excellent cooperation with the authorities and we believe that we fulfill the requirements with high transparency. That is our aim and also the aim of our partners, because we understand the problems and take them seriously”, Berge Olsen states.

wpd has developed the Butendiek project and is one of the shareholders and also the competent project manager during construction and operation. Preparation for the works in the construction site have begun in March 2014, in the fall of 2014, the first wind turbines will be implemented and taken into operation continually, construction is scheduled to be completed in the summer of 2015. The Butendiek offshore wind farm will provide some 370,000 households with renewable energy. 

Key Facts for the Butendiek Offshore Wind Farm:

  • 80 turbines with a total capacity of 288 MW
  • Situated in the German North Sea some 32 km to the west of the island of Sylt
  • Shallow waters (17 – 22 meters) and favorable ground conditions
  • Cooperation with well-known suppliers: Siemens (Siemens SWT 3.6-120 turbines), Ballast Nedam (monopiles), Visser Smit (internal park cabling), Farbricom/GdF Suez (substation)
  • Grid connection via the SylWin-Cluster
  • Commissioning: Continuous commissioning following the installation of the turbines in the fall of 2014; completion of the OWP Butendiek in June 2015
  • Power generation: some 1,290 GWh/a, equaling supply to some 370,000 households
  • Total investment sum: 1.3 billion Euros

Contact:
wpd AG
Christian Schnibbe
Stephanitorsbollwerk 3 (Haus LUV)
28217 Bremen
Germany
Phone: +49 (421) 16866-2500c.schnibbe(et)wpd.de